In VBA I want to convert a date as 03/11/2017(DD/MM/YYYY) into the week number for that date.
Until now I have the following code:
'geting the date out of the string
HeadlineTemp = Mid(VRHeadline, InStr(VRHeadline, "[") + 1, 10)
'switch "." to "/"
HeadlineTemp = Replace(HeadlineTemp, ".", "/")
'convert to a date
FristVRFirstKW = CDate(HeadlineTemp)
Now, I need a function to convert that date into the week number of the year. First week day is Monday.
要将星期一作为第一天的周数,请使用以下内容:
WorksheetFunction.WeekNum(now, vbMonday)
Using VBA, to convert a date into an isoWeeknumber, you merely need the DatePart
function (where DT is the date of interest):
isoWeekNumber = DatePart("ww", DT, vbMonday, vbFirstFourDays)
If you want to use other definitions than that specified in ISO 8601, investigate some of the other options for FirstDayOfWeek
and FirstWeekOfYear
NOTE
As pointed out by @Mike85, there is a bug in DatePart
(and also in the Format
) function wherein Monday may be erroneously given a weeknumber of 53 when it should be 1.
There are a variety of workarounds.
In Excel 2013+ (Excel for Mac 2011+) you can use for the ISO Weeknumber:
isoWeekNumber = WorksheetFunction.isoWeekNum(dt)
For earlier versions, you can test the Monday and adjust it if necessary, or you can write a separate routine.
Be carefull when it comes to week numbers as there are different definitions around. The Excel definition differs from the ISO definition. To get the ISO weeknumber use (copied From http://www.rondebruin.nl/win/s8/win001.htm )
Public Function IsoWeekNumber(d As Date) As Integer
Dim d2 As Long
d2 = DateSerial(Year(d - Weekday(d - 1) + 4), 1, 3)
IsoWeekNumber = Int((d - d2 + Weekday(d2) + 5) / 7)
End Function
WeekdayName( number, [abbreviate], [firstdayofweek] ) WeekdayName(2)
Result: 'Monday'
WeekdayName(2, TRUE)
Result: 'Mon'
WeekdayName(2, TRUE, vbMonday)
Result: 'Mon'
So, this is my final and working perfectly version
Public Function IsoWeekNumber(d As Date) As String
Dim kwtemp As String
kwtemp = DatePart("ww", d, vbMonday, vbFirstFourDays)
If Len(kwtemp) = 1 Then kwtemp = "0" & kwtemp
IsoWeekNumber = kwtemp
End Function
If Application.International(xlMDY) = True Then
HeadlineTemp = Mid(VRHeadline, InStr(VRHeadline, "[") + 1, 10)
HeadlineTemp = Replace(HeadlineTemp, ".", "/")
HeadlineTemp = Mid(HeadlineTemp, 4, 3) & Left(HeadlineTemp, 2) & Right(HeadlineTemp, 5)
VRFirstKW = CDate(HeadlineTemp)
HeadlineTempEndKW = Mid(VRHeadline, InStr(VRHeadline, "]") - 10, 10)
HeadlineTempEndKW = Replace(HeadlineTempEndKW, ".", "/")
HeadlineTempEndKW = Mid(HeadlineTempEndKW, 4, 3) & Left(HeadlineTempEndKW, 2) & Right(HeadlineTempEndKW, 5)
VREndKW = CDate(HeadlineTempEndKW)
VRKW = "KW" & IsoWeekNumber(VRFirstKW) & "-" & IsoWeekNumber(VREndKW) & "/" & Year(VREndKW)
Else 'don't switch position of the month with days
HeadlineTemp = Mid(VRHeadline, InStr(VRHeadline, "[") + 1, 10)
HeadlineTemp = Replace(HeadlineTemp, ".", "/")
VRFirstKW = CDate(HeadlineTemp)
HeadlineTempEndKW = Mid(VRHeadline, InStr(VRHeadline, "]") - 10, 10)
HeadlineTempEndKW = Replace(HeadlineTempEndKW, ".", "/")
VREndKW = CDate(HeadlineTempEndKW)
VRKW = "KW" & IsoWeekNumber(VRFirstKW) & "-" & IsoWeekNumber(VREndKW) & "/" & Year(VREndKW)
Calculate ISO year using datepart with bugs workaround:
'Test 2007-12-31 should return W01Y2008
myDate = "2007-12-31"
ISOWeek = DatePart("ww", myDate, vbMonday, vbFirstFourDays)
Week1 = DatePart("ww", myDate, vbMonday, vbFirstFourDays)
Week2 = DatePart("ww", DateAdd("d", 7, myDate), vbMonday, vbFirstFourDays)
ISOYear = DatePart("yyyy", myDate, vbMonday, vbFirstFourDays)
Year1 = DatePart("yyyy", myDate, vbMonday, vbFirstFourDays)
Year2 = DatePart("yyyy", DateAdd("d", 7, myDate), vbMonday, vbFirstFourDays)
If ISOWeek = 53 And DatePart("ww", DateAdd("d", 7, myDate), vbMonday, vbFirstFourDays) = 2 Then
ISOWeek = 1
End If
if ISOWeek = 1 And DatePart("yyyy", DateAdd("d", 7, myDate), vbMonday, vbFirstFourDays) > ISOYear Then
ISOYear = ISOYear + 1
End If
MsgBox("W" & ISOWeek & "Y" & ISOYear)
' Result in W01Y2008
Cw = DatePart("ww", d, vbWednesday, vbFirstFullWeek)
ww -> for Calendar Week
d -> date variable
vbWednesday -> Starting day of week
vbFirstFullWeek -> year will be started from first 7
This alternate solution assumes the week number increases by 1 each Monday, and resets to 1 on the first Monday in January.
Dim WeekNumber as long
WeekNumber = Int(DateDiff("d", CDate("1/1/" & Year(DateAdd("d", 1 - Weekday(Date, 2), Date))), DateAdd("d", 1 - Weekday(Date, 2), Date)) / 7) + 1