Anylogic: avoid unwanted execution of process in seize block

I am trying to simulate manufacturing process by using statechart. And i have created agents for particular machines by statecharts and connecting those agents according to manufacturing process with help of resource pool, seize block and release block

在此处输入图像描述

My agent is passing through the resource pool and seize block. And I am expecting to run the model one after another seize blocks. However, when I run the model my all three statcharts are active at a same time, which I do not want. can anybody suggest me a possible way to avoid simultaneous process?

I'm assuming your manufacturing processes don't take 0 time. You're missing Delay blocks, causing all your blocks to execute at the same, instantaneous moment.

On a side note, what you're showing us isn't a statechart , but a flowchart.

The technical post webpages of this site follow the CC BY-SA 4.0 protocol. If you need to reprint, please indicate the site URL or the original address.Any question please contact:yoyou2525@163.com.

 
粤ICP备18138465号  © 2020-2024 STACKOOM.COM