简体   繁体   中英

How to group by a Calculated Field

I need to group by a Calculated field ins SQL Server 2005/2008.

I have the following sql:

select dateadd(day, -7, Convert(DateTime, mwspp.DateDue) + (7 - datepart(weekday, mwspp.DateDue))),
sum(mwspp.QtyRequired)
from manufacturingweekshortagepartpurchasing mwspp
where mwspp.buildScheduleSimID = 10109 and mwspp.partID = 8366
group by mwspp.DateDue
order by mwspp.DateDue

Instead of group by mwspp.DateDue I need to group by the result of the calculation. Is it possible ?

Thanks in advance

Sure, just add the same calculation to the GROUP BY clause:

select dateadd(day, -7, Convert(DateTime, mwspp.DateDue) + (7 - datepart(weekday, mwspp.DateDue))),
sum(mwspp.QtyRequired)
from manufacturingweekshortagepartpurchasing mwspp
where mwspp.buildScheduleSimID = 10109 and mwspp.partID = 8366
group by dateadd(day, -7, Convert(DateTime, mwspp.DateDue) + (7 - datepart(weekday, mwspp.DateDue)))
order by dateadd(day, -7, Convert(DateTime, mwspp.DateDue) + (7 - datepart(weekday, mwspp.DateDue)))

Edit after comment:

Like all questions regarding the optimiser, the answer is really "it depends", but most likely it will only be performed once - you'll see this in the execution plan as a Compute Scalar operator.

Based on this Compute Scalar operation, the optimiser will then decide how to perform the actual aggregation.

The other answers here (CTE/subquery, etc) are all equally valid, but don't really change the logic - ultimately they will be performing similar operations. SQL Server might treat them differently but it's unlikely. However they will help with readability.

If you're worried about efficiency you can look at a couple of options, eg setting up the calculation as a persisted computed column and using this in an index, or adding interim results into a temporary table.

The only way to really know for sure is to inspect the Execution Plan/IO statistics when running the query on a typical data set and seeing if you're satisfied with the performance; if not, perhaps investigating one of the above options.

If you want to GROUP BY the dateadd calculation, then you will either need to place that formula in the GROUP BY clause or you can wrap your query in another SELECT:

select DateCalc,
  sum(QtyRequired) TotalQty
from
(
  select mwspp.DateDue,
    dateadd(day, -7, Convert(DateTime, mwspp.DateDue) + (7 - datepart(weekday, mwspp.DateDue))) DateCalc,
    mwspp.QtyRequired
  from manufacturingweekshortagepartpurchasing mwspp
  where mwspp.buildScheduleSimID = 10109 
    and mwspp.partID = 8366
) src
group by DateCalc
order by DateCalc

There are several ways of doing so - one involves using a CTE:

with cte as 
(select m.*, 
        dateadd(day, -7, Convert(DateTime, DateDue) + (7 - datepart(weekday, DateDue))) datecalc
 from manufacturingweekshortagepartpurchasing m)
select datecalc, sum(QtyRequired)
from cte
where buildScheduleSimID = 10109 and partID = 8366
group by datecalc
order by datecalc

Simply place the calculation in the GROUP BY clause:

Replace

group by mwspp.DateDue

To

group by dateadd(day, -7, Convert(DateTime, mwspp.DateDue) + (7 - datepart(weekday, mwspp.DateDue)))