Scheduling a SQL Job

what is the best way to schedule a SQL Job to run from (any date range) ie 15th to 18th every single month with no end date?

Thanks in advance.

john

SQL Server 2008 you can set the frequency to occur Monthly and have 3 or 4 individual schedules to occur on the 15th, 16th, 17th, and 18th day of each month. Similar to the below image.

在此处输入图片说明

Not the cleanest solution but it does work.